Development Schedule:


               

Engineering Detailed Design:             Completion December 2013

Construction Tendering:                   Completion March 2014

Lot Lottery / Pre-Sales:                    Completion March 2014

Grading & Earthworks Const:            Completion June 2014                        

Underground Construction:              Completion mid August 2014

Roadway Const: (excl paving):          Completion September 2014

Roadway Paving:                              Completion June 2015

 

 